Closed
50cm wide, 70cm long, 20cm deep hole between two driveways
Reported via desktop in the Damaged pavement category by Stephen Tiller at 17:56, Wed 30 October 2024
Sent to London Borough of Bexley less than a minute later. Report ref: 6677245.
This hole between driveways was reported on 17-06-2022 and a contractor was sent to remedy, all they did was put some hardcore in the hole. They run out of asphalt so they closed the job ! Could this job be finished please.
Updates
-
State changed to: Investigating
Posted by London Borough of Bexley at 08:09, Thu 31 October 2024
-
Following further investigations, we can confirm that the issue identified in this report does not currently exceed the Council's threshold where further action would be required at this stage. Further information on these guidelines can be found on our website:
Highways Service Level Agreements
We will continue to monitor the situation and take the necessary steps if and when the issue does meet the Councils requirements for action.
If you feel the problem deteriorates or requires further investigation in the future, please let us know.
We thank you for reporting this matter for our attention.
State changed to: No further action
Posted by London Borough of Bexley at 14:01, Wed 27 November 2024
This report is now closed to updates from the public. You can make a new report in the same location.