Action scheduled
Road surface has sunk approx 10 inches
Reported via mobile in the Damaged road category anonymously at 23:14, Tue 7 May 2024
Sent to London Borough of Bexley less than a minute later. Report ref: 5943787.
On the road surface outside 2 Sandringham Drive Welling, after a minor fix was carried out by partially filling the surface, the road surface has rapidly sunk down approximately ten to twelve inches across a space of about two to three feet.
This is a major risk to anyone on two wheels and could cause significant damage to a 4 wheeled vehicle.
Updates
-
State changed to: Investigating
Posted by London Borough of Bexley at 08:01, Wed 8 May 2024
-
This case has been referred to the Council’s contractor and will be completed within the Council’s contractual service level arrangements.
We will update the case once it has been completed.
Thank you for reporting this matter.
State changed to: Action scheduled
Posted by London Borough of Bexley at 16:10, Wed 8 May 2024
-
The hole has got substantially worse with a void appearing underneath. Cars are bottoming out on the tarmac causing their chassis to hit the ground, cyclists have come off their bike and an elderly person fell over when crossing the road.
Contractors came yesterday to put cones out as they said it would be being repaired today but then returned and took the cones and signs away with no explanation.
Posted anonymously by a non-staff user at 18:25, Wed 15 May 2024
-
State changed to: Investigating
Posted by London Borough of Bexley at 09:28, Thu 16 May 2024
-
This case has been referred to the Council’s contractor and will be completed within the Council’s contractual service level arrangements.
We will update the case once it has been completed.
Thank you for reporting this matter.
State changed to: Action scheduled
Posted by London Borough of Bexley at 16:53, Thu 16 May 2024
-
Questionnaire filled in by problem reporter
State changed to: Fixed
Posted anonymously by a non-staff user at 01:04, Wed 5 June 2024
-
This case has been referred to the Council’s contractor and will be completed within the Council’s contractual service level arrangements.
We will update the case once it has been completed.
Thank you for reporting this matter.
State changed to: Action scheduled
Posted by London Borough of Bexley at 01:05, Wed 5 June 2024
Only the original reporter may leave updates. If you made the original report please log in to leave an update.