Reported via mobile in the Damaged road category anonymously at 19:14, Sun 27 March 2022

Sent to London Borough of Bexley less than a minute later. Report ref: 3419652.

Horley close has pot holes and causes damage to the tyres and wheels

RSS feed of updates to this problem Receive email when updates are left on this problem.

Updates

  • This case is currently being investigated.

    Further updates will follow.

    State changed to: Investigating

    Posted by London Borough of Bexley at 09:18, Mon 28 March 2022

  • The reported issue requires further evidence or investigation, and as such will be monitored by our Highways Technicians.

    A re-inspection has been scheduled for a future date, which will determine if any action will be undertaken.

    Thank you for reporting this matter.

    State changed to: Action scheduled

    Posted by London Borough of Bexley at 08:18, Tue 29 March 2022

  • Please see attached as requested.

    Posted anonymously by a non-staff user at 17:46, Wed 6 April 2022

  • Still open, via questionnaire, 20:45, Sun 24 April 2022

  • Its been over 8 weeks and no action

    Posted anonymously by a non-staff user at 21:29, Sun 22 May 2022
    Still open, via questionnaire

  • This was logged 4 months ago and is still outstanding. Ridiculous no call or are any repairs carried out

    Posted anonymously by a non-staff user at 22:00, Sun 19 June 2022
    Still open, via questionnaire

  • Still open, via questionnaire, 04:03, Mon 18 July 2022

  • Still open, via questionnaire, 22:36, Mon 15 August 2022

  • This case has been referred to the Council’s contractor and will be completed within the Council’s contractual service level arrangements.

    We will update the case once it has been completed.

    Thank you for reporting this matter.

    Posted by London Borough of Bexley at 06:45, Sun 18 September 2022

  • The pot holes and cracks still remian. No onr had come to look at the road

    State changed to: Fixed

    Posted anonymously by a non-staff user at 06:45, Sun 18 September 2022

  • This case is currently being investigated.

    Further updates will follow.

    State changed to: Investigating

    Posted by London Borough of Bexley at 10:17, Tue 20 September 2022

  • The reported issue requires further evidence or investigation, and as such will be monitored by our Highways Technicians.

    A re-inspection has been scheduled for a future date, which will determine if any action will be undertaken.

    Thank you for reporting this matter.

    State changed to: Action scheduled

    Posted by London Borough of Bexley at 17:05, Thu 22 September 2022

  • The report has been inspected by a member of the Highways Team . The inspection concluded that the fault identified within this report does not require further action as it does not meet guidelines where further action or repairs are required at this stage.

    Highways Service Level Agreements

    Thank you for reporting this matter.

    State changed to: No further action

    Posted by London Borough of Bexley at 07:45, Mon 19 December 2022

This report is now closed to updates. You can make a new report in the same location.