Fixed
Blocked drain adjacent to no 2 Tyron Way
Reported via desktop in the Blocked rainwater gulleys category anonymously at 11:13, Mon 28 December 2020
Sent to London Borough of Bexley less than a minute later. Report ref: 2449332.
This drain has had to take drainage water from Building site at corner house in Langdon Shaw where there have been spills on concrete and mud and CLAY now causing drain to be very slow to clear road water when it rains. Drain needs to cleared and site opposite needs to be looked at.
Updates
-
State changed to: Investigating
Updated by London Borough of Bexley at 07:27, Tue 29 December 2020
-
State changed to: Action scheduled
Updated by London Borough of Bexley at 12:00, Wed 6 January 2021
-
No evidence that this problem has been visited or any action taken.
Posted anonymously by a non-staff user at 11:13, Tue 26 January 2021
Still open, via questionnaire -
Updated by London Borough of Bexley at 13:09, Tue 23 February 2021
-
Still no evidence that this problem has been looked at or any action taken loose debris continues to be washed into the drains, also the drain outside no 6 Tyron Way. Also drains further along the road have similar problems outside Nos 49 55 and 84 Tyron Way.
Posted anonymously by a non-staff user at 13:09, Tue 23 February 2021
Still open, via questionnaire -
Updated by London Borough of Bexley at 14:25, Tue 23 March 2021
-
Nope still no evidence that these and other drains in Tyron Way have been cleared.
Posted anonymously by a non-staff user at 14:25, Tue 23 March 2021
Still open, via questionnaire -
Questionnaire filled in by problem reporter; State changed to: Fixed, 19:18, Tue 20 April 2021
-
The case has been resolved.
Thank you for reporting this matter.
State changed to: Fixed
Posted by London Borough of Bexley at 00:00, Tue 12 April 2022
This report is now closed to updates from the public. You can make a new report in the same location.