Closed
Potholes
Reported via iOS in the Damaged road category anonymously at 14:08, Tue 2 June 2020
Sent to London Borough of Bexley less than a minute later. Report ref: 2139299.
Potholes
Updates
-
State changed to: In progress
Updated by London Borough of Bexley at 15:16, Tue 2 June 2020
-
This case is currently being investigated
State changed to: Investigating
Posted by London Borough of Bexley at 07:27, Wed 3 June 2020
-
We have inspected the fault and determined that it does not meet the guidelines for further action at the moment.
Thank you for reporting this matter.
State changed to: No further action
Posted by London Borough of Bexley at 00:00, Thu 4 June 2020
-
This case has been resolved.
State changed to: Fixed
Posted by London Borough of Bexley at 08:42, Thu 4 June 2020
-
This case has not been resolved
State changed to: Open
Posted anonymously by a non-staff user at 15:45, Tue 28 July 2020
Still open, via questionnaire -
Still open, via questionnaire, 23:04, Tue 8 September 2020
-
Still open, via questionnaire, 23:40, Tue 6 October 2020
-
Still there.
Posted anonymously by a non-staff user at 00:11, Wed 4 November 2020
Still open, via questionnaire -
Still open, via questionnaire, 01:02, Wed 2 December 2020
-
Still open, via questionnaire, 01:32, Wed 30 December 2020
-
Still open, via questionnaire, 08:44, Wed 27 January 2021
-
Still open, via questionnaire, 09:14, Wed 24 February 2021
-
Still open, via questionnaire, 09:43, Wed 24 March 2021
-
Still no fix
Posted anonymously by a non-staff user at 10:06, Wed 21 April 2021
Still open, via questionnaire -
Work to resolve the issue you raised and undertaken on a priority basis. We cannot provide specific
timescales but aim to get this matter resolved as soon as possible, and we will notify you.Thank you for bringing to our attention.
State changed to: Action scheduled
Posted by London Borough of Bexley at 11:17, Fri 23 April 2021
-
Work to resolve the issue you raised and undertaken on a priority basis. We cannot provide specific
timescales but aim to get this matter resolved as soon as possible, and we will notify you.Thank you for bringing to our attention.
Posted by London Borough of Bexley at 12:33, Wed 19 May 2021
-
Questionnaire filled in by problem reporter
State changed to: Fixed
Posted anonymously by a non-staff user at 12:33, Wed 19 May 2021
-
Work to resolve the issue you raised and undertaken on a priority basis. We cannot provide specific
timescales but aim to get this matter resolved as soon as possible, and we will notify you.Thank you for bringing to our attention.
State changed to: Action scheduled
Posted by London Borough of Bexley at 03:00, Thu 20 May 2021
-
We have inspected the fault and determined that it does not meet the guidelines for further action at the moment.
Thank you for reporting this matter.
State changed to: No further action
Posted by London Borough of Bexley at 00:00, Thu 21 July 2022
This report is now closed to updates from the public. You can make a new report in the same location.